Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56662 REL 12: 2009-001-00 EXP EXPANDED MULTI-SPECIES ACCLIMATION
Project Number:
Title:
Upper Columbia Spring Chinook and Steelhead Acclimation
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Columbia Cascade Methow 50.00%
Wenatchee 50.00%
Contract Number:
56662 REL 12
Contract Title:
2009-001-00 EXP EXPANDED MULTI-SPECIES ACCLIMATION
Contract Continuation:
Previous: Next:
55960: 2009-001-00 EXP EXPANDED MULTI-SPECIES ACCLIMATION
  • 56662 REL 45: 2009-001-00 EXP EXPANDED MULTI-SPECIES ACCLIMATION
Contract Status:
Closed
Contract Description:
For the 2013 Expanded & Multispecies Acclimation (EMSA) contracting period, YN will focus on a limited scope of work as for acclimated release groups within the Methow and Wenatchee subbasins.  Due to site restrictions within the Mid-Columbia Coho Reintroduction Program (MCCRP), the Rohlfing's site will not be available for co-mingling steelhead with coho.  The Methow will continue to release spring Chinook, as a part of the DCPUD/GCPUD's mitigation for Methow spring Chinook, at the Mid-Valley Pond site, located approximately 5 miles upstream from the Methow FH.  This will be the second year of use and intended to distribute spring Chinook production further upstream to alleviate spawner densities issues currently documented within this program.  Also, a composite of spring Chinook and coho will be co-reared in the Winthrop NFH back channel, as done for the past couple of years.  The intent here is to continue to gain valuable information regarding potential benefits, both biologically and from a cost perspective, of maximizing limited rearing space within the Upper Columbia (UC) region.  Both treatment groups will have comparable controlled releases from both the Methow FH as well as Winthrop NFH.  Some of the performance metrics identified as part of YN's evaluation would be in-pond survival, release-to-McNary survival, and overall release timing/condition for each species.

In addition to the on-the-ground activities, YN will be pursuing multiple site developments in both the Wenatchee and Methow for long-term implementation once the data has been summarized and accepted within the co-managers.  Initial reporting of results have been positive and this long-term implementation for both spring Chinook and steelhead would be consistent with future HGMPs as well as long-term implementation of recalculated release/production goals through mitigation discussions.  Examples of these sites would be on the Chewuch, Upper Methow, and in Nason Creek.
Account Type(s):
Expense
Contract Start Date:
02/01/2013
Contract End Date:
01/31/2014
Current Contract Value:
$253,702
Expenditures:
$253,702

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Roy Beaty Bonneville Power Administration Yes COR rebeaty@bpa.gov (503) 230-5213
Michelle Guay Bonneville Power Administration No Interested Party mxguay@bpa.gov (503) 230-3459
Tana Hoptowit Yakama Confederated Tribes No Interested Party hopt@yakamafish-nsn.gov (509) 865-5121x6318
Cory Kamphaus Yakama Confederated Tribes Yes Contract Manager kamc@yakamafish-nsn.gov (509) 548-9413x102
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Keely Murdoch Yakama Confederated Tribes Yes Technical Contact murk@yakamafish-nsn.gov (509) 548-2206
Thomas Scribner Yakama Confederated Tribes Yes Supervisor scrt@yakamafish-nsn.gov (503) 331-9850
Paul Ward Yakama Confederated Tribes No Supervisor warp@yakamafish-nsn.gov (509) 949-4129
Nancy Weintraub Bonneville Power Administration No Env. Compliance Lead nhweintraub@bpa.gov (503) 230-5373


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Produce plan for 2014 spring Chinook and steelhead B: 174. 2014 Multispecies rearing plan 01/31/2014 01/31/2014
Final Site List compliance for acclimation C: 165. Final site list compliance for acclimation 10/01/2013 10/01/2013
Data Collection and Analysis D: 157. Collect Water Quality Data 07/01/2013 07/01/2013
Fulfill all administrative tasks with quality products and in a timely manner. E: 119. Manage Expanded Acclimation Project 01/31/2014 01/31/2014
Stakeholder Coordination F: 191. Coordination of Plan with Regional Stakeholders 01/31/2014 01/31/2014
Annual comprehensive report to cover activities from 3/1/12 to 12/31/12 G: 132. Annual synopsis report for 2013 releases; developed as a technical memo or summary of findings 01/31/2014
PIT tag spring Chinook and/or steelhead H: 158. Tag up to 42K steelhead and/or spring Chinook in the Wenatchee and Methow basins for 2014 releases 12/01/2013 12/01/2013
acclimate spring Chinook in CY2013. I: 176. Acclimate spring Chinook at Mid-Valley Pond and Winthrop NFH back channel 06/30/2013 06/30/2013
Development of Squadroni Pond or Whitepine location J: 171. Develop additional site in Nason Creek for Wenatchee steelhead production 01/31/2014
Development of a acc. site in the upper Methow or Chewuch K: 171. Develop additional site in upper Methow and/or Chewuch for Methow steelhead and/or spring Chinook 01/30/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 1 instance of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 174 Produce Plan
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 2 instances of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/01/2013
B 174 2014 Multispecies rearing plan 02/01/2013
C 165 Final site list compliance for acclimation 02/01/2013
D 157 Collect Water Quality Data 02/01/2013
E 119 Manage Expanded Acclimation Project 02/01/2013
F 191 Coordination of Plan with Regional Stakeholders 02/01/2013
G 132 Annual synopsis report for 2013 releases; developed as a technical memo or summary of findings 02/01/2013
H 158 Tag up to 42K steelhead and/or spring Chinook in the Wenatchee and Methow basins for 2014 releases 02/01/2013
I 176 Acclimate spring Chinook at Mid-Valley Pond and Winthrop NFH back channel 02/01/2013
J 171 Develop additional site in Nason Creek for Wenatchee steelhead production
K 171 Develop additional site in upper Methow and/or Chewuch for Methow steelhead and/or spring Chinook